5.3
Erection and assembly
Check as follows:
•
Check all fixing screws
•
Check all safety fasteners, and remove any foreign bodies from the Milling chamber.
Check electric system (only by an electrician)
•
Operating voltage using a voltmeter
•
Electrical fuses
•
Check electric cables for any signs of damage
•
Check connections
•
Connect up the machine according to the circuit diagram.
•
Check proper position of Mortar and Pestle
6.1
Connection
These jobs of work may only be carried out by qualified staff. The connections must be completed carefully.
Errors can pose a mortal danger. The connection regulations of the responsible power utility company must
be observed.
5.4
Erection site
The machine can be easily moved within the laboratory or the workshop.
The following points must be observed at the erection site of the machine:
•
A constant temperature must be guaranteed. It should not be under +5°C or above +40°C.
•
The humidity may not exceed 85% continuously.
•
The main switch of the Mortar Grinder must be freely accessible.
5.5
Taking the Mortar Grinder into storage.
The Mortar Grinder is to be stored in a dry room. Protect from the damp, from a corrosive atmosphere and from
temperatures below +5°C and above +45°C.
6
Electrical connection
When connecting the machine to your local power supply source please pay attention to the information on the sticker at the
rear of the machine showing the technical information.
6.2
Starting up the Mortar Grinder
Only start the Mortar Grinder with properly inserted Mortar and Pestle.
10
LMMG100 MORTAR GRINDER MANUAL