1-41
GENERAL MAINTENANCE
PACKER REMOVAL
PROCEDURE
19. Fold the follower panels over the
packer.
20. Weld the follower panels to the
packer.
21. Attach the packer to a lifting device
(Fork lift) in order to extract it
from the hopper.
22. Re-install the new packer into the
hopper checking the alignment of
the packer with the floor guides.
23. Install a new wiper blade on each
side of the packer (Figure #1.58).
These wiper blades may require to
be adjusted to fit between the new
packer and the hopper walls.
24. Once the packer is installed in the
hopper, install roller assemblies
and reverse the procedure to
reconnect the hydraulic cylinders
and re-install both side rails.
25. Stitch weld the rails along the top
edge of the hopper wall (Figure
#1.44).
26. Once finished re-assembling the
removed components, lubricate
and check for proper operation of
the packer.
FIGURE #1.58
DANGER
DO NOT CLIMB INTO THE
HOPPER WHILE THE PACKER IS
MOVING.
FIGURE #1.57
DANGER
APPLY THE LOCKOUT / TAGOUT
PROCEDURE AT ALL TIMES WHEN
MAINTENANCE OR INSPECTION IS
CARRIED OUT ON THE VEHICLE.
DANGER
SECURE THE AREA AROUND THE
PATH OF THE ARM WHEN
PERFORMING MAINTENANCE OR
REPAIR.
1.12.6
PACKER REMOVAL (cont’d)
WIPER BLADE
(PLASTIC)
Summary of Contents for Automizer Versa Hand
Page 2: ...AUTOMIZER VERSA HANDTM 1 2...
Page 4: ...AUTOMIZER VERSA HANDTM 1 4...
Page 8: ...AUTOMIZER VERSA HANDTM 1 8...
Page 58: ...AUTOMIZER VERSA HANDTM 1 58 FIGURE 1 81 INPUT OUTPUT COVER ELECTRICAL COILS...
Page 69: ...1 69 GENERAL MAINTENANCE FIGURE 1 89A Strainer Seal...
Page 77: ...1 77 GENERAL MAINTENANCE A B C BEHIN D D F MAIN RELIEF B E...
Page 105: ...1 105 GENERAL MAINTENANCE NOTES...