LAGUNATOOLS.COM
29
NOTE:
Conveyor belt will require (periodic) adjustment to maintain proper
tacking on conveyor bed. Adjust by tightening the adjustment stud, Fig. 21,
with a
5mm Hex Wrench
) on the side the belt is drifting toward and loosen
the opposite side an equal rotation.
NOTE:
Make tracking adjustments before conveyor belt rubs on side of
conveyor bed.
Figure 21: Conveyor Tracking
9. Each brush head has independent RPM Adjustment, (Fig. 10). While the
brush is running, rotate the handle above each motor to adjust RPM. Confirm
correct RPM setting with sample testing information or your salesperson. RPM
reads out on yellow indicator near motor along column.
Excessive RPM will prematurely shorten brush life!
10. Start dust collector (open blast gates if so equipped).
11. Place material on conveyor and maintain control of stock until the
tension roller is holding stock properly.
12. To stop, press the
“
OFF
”
buttons for the brush and conveyor, Fig. 20.
Press the “E
-
STOP”
button if there is an Emergency, Fig. 20! To reset the E-
STOP button, twist and pull back on the button.
Tracking Stud
(2)
Summary of Contents for SuperMax SuperBrush 24 x 2
Page 1: ...OWNERS S MANUAL SuperBrush 24 x 2 SuperBrush 36 x 2 Lagunatools com...
Page 25: ...LAGUNATOOLS COM 25 INTERNAL WIRING Figure 15 Internal Wiring...
Page 34: ...LAGUNATOOLS COM 34 Exploded Views STAND ASSEMBLY 1of 2 Figure 22 Stand Assembly...
Page 39: ...LAGUNATOOLS COM 39 HEAD ASSEMBLY Front 1 2 Figure 24 Head Assembly Front 1 2 without brush...
Page 42: ...LAGUNATOOLS COM 42 CONVEYOR ASSEMBLY Figure 25 Conveyor Assembly...