9.
Check alignment (parallelism)
of the brush head to the conveyor. Measure
from the bottom of the brush bristles to the top of the conveyor belt on the right
and left side. If the brush head is not parallel;
A. loosen the two bearing bolts (that secure the bearing to the machine)
on the lower side of the brush, Fig. 8.
B. Raise the bearing on the low side by using a hex wrench in the center
of the bearing stud and rotate both equally until the brush head is
parallel.
C. Tighten the bolts attaching the bearing to the machine bracket.
Figure 8: Aligning Brush Head
Dust Collection, Connection/Assembly
1. Connect dust collection
hose to each 4” port on machine. Minimum of *600
CFM per port.
*NOTE: The CFM requirement can vary depending on brush head, application(s)
and material.
Figure 9: Dust Ports
Bearing Bolts
Bearing Stud
Dust Ports (3)
Summary of Contents for SuperMax SuperBrush 49
Page 1: ...OWNERS S MANUAL SuperBrush 49 Lagunatools com...
Page 23: ...LAGUNATOOLS COM 23 WIRING DIAGRAMS POWER CONNECTIONS Figure 14 Power Connections Wiring...
Page 24: ...LAGUNATOOLS COM 24 INTERNAL WIRING Figure 15 Internal Wiring...
Page 30: ...LAGUNATOOLS COM 30 Exploded Views STAND ASSEMBLY Figure 22 Stand Assembly...
Page 33: ...LAGUNATOOLS COM 33 HEAD ASSEMBLY Figure 23 Head Assembly without brush...
Page 35: ...LAGUNATOOLS COM 35 CONVEYOR ASSEMBLY Figure 24 Conveyor Assembly...