3 PHASE SUPPLY - FOR INSTALLATION IN MAINLAND EUROPE
For connection to a 3 phase supply, the supplied mains cable and bridging link
will need to be removed.
• Firstly open the terminal block cover using a small flat bladed screwdriver
•
Remove cable clamp screw and remove mains cable
•
Remove 1 bridging link from terminals L1 and L2
MAINS CABLE TO BE REMOVED
CABLE CLAMP
THIS LINK TO BE REMOVED
Fit 3 phase mains cable in terminal block as shown in table below;
Wire
Connect to:
L1
L1
L2
L2
L3
*See note below
Neutral
N1 or N2
Earth
* L3 is not required on these appliances. Please ensure L3 is terminated safetly inside terminal
cover
•
Fit the cable clamp & secure with the screw provided.
•
Close the terminal box, ensuring that the cover is closed and all screws are tight and in place.
Summary of Contents for LAM1800
Page 2: ......
Page 28: ...Product serial number Place sticker here ISSUE V2 070217 ...