Initial Set-Up
Pre-Operation Equipment Inspection Checklist
Initial Set-Up
8/23/22
3-22
3
3.24 Pre-Operation Equipment Inspection Checklist
Perform the following equipment inspection
prior to each operation
of the Lastec
Mower:
Verify that the parking brake is set.
Check the fuel level.
Check engine oil level and condition.
Check the air cleaner and filter elements for contamination or debris.
Brush out and clean the radiator screen.
Clean entire mower deck area under operator seat pan of any grease, oil, fuel, grass, or debris.
Check coolant level and condition in overflow tank.
Check hydraulic fluid level and condition.
Add if low - do not overfill.
Change oil and filter if necessary.
Inspect the entire hydraulic system for leaks.
Adjust hydrostatic pumps if needed.
Check both hydrostatic pump belts and tension springs for proper installation and condition.
Check the mower deck drive belt and idler tension spring for proper installation and condition.
Check all mower deck belts and idler tension springs for proper installation and condition.
Inspect all blades for proper installation, orientation, tightness, sharpness, and overall condition.
Be sure the seatbelt is secure and operable.
Be sure the operator seat pan and engine cover are properly closed, latched, and secure.
Adjust the operator seat for proper operator position.
Ensure both steering control levers are properly linked, free of debris, and operating freely.
Set the mower deck height to the desired level.
Calibrate the mower deck height adjustment rods if needed.
Check the air pressure in the rear drive tires.
Verify proper function of all wheels.
Verify that all warning decals are in place, visible, and legible.
Verify that all covers and safety devices are properly installed and secure.
Ensure the discharge chute is clear of debris, properly mounted, and in good condition.
Inspect entire Lastec Mower for loose or entangled parts, debris, obstructions, or neglected tools.
Check engine for abnormal exhaust or sounds.
Record the hour meter setting if desired.
Complete the appropriate maintenance checklist (section 5).