Starting / Shutting down
Part 1 • Page 8-1
Part 1 – Operating Instructions
Rev. 4.00 December 2014
Software version 1.04
EcoRO Dia I/II (HT)
Part 1 • Chapt
er 8
8.
Starting / Shutting down
When the device is open:
•
Commissioning, operation and maintenance is only to be carried out by authorized, trained and
LMW-instructed skilled workers. Electrical work is to be carried out only after completely disconnecting
the system from the power supply and only by authorized, trained and instructed electricians.
•
Read and carefully observe these operating instructions, especially the safety instructions
chapter 1 ff. before starting up, operating and servicing the system.
•
When putting into operation, check to make sure all water connections have been made properly
part 2, chapter 3 and that all connections are leakproof.
8.1
Machine start-up
Open the water feed (upstream of the system) and switch the system to
ON
at the main switch.
1. Switch operating mode selection switch to 1 (dialysis mode).
2. The control unit switches the pumps on and the system starts to produce permeate.
8.2
Interruption in production
The system can be left filled with water for a short time e.g. overnight, if it is not to be operated in the
standby mode.
The system should be switched on some time before the first dialysis to rinse out the system and loop.
8.3
Machine start-up after shutdown due to a fault
If the system is at a standstill due to a fault, the cause will be shown on the display. The cause of the fault
must be eliminated if possible
The control system may need to be reset, depending on the problem. This is done by switching the main
switch off and on again or by pressing the reset key on the display.
WARNING
High voltage
NOTICE
However, there is an increased risk of contamination in the system and loop in this case.
IMPORTANT After the RO has been at a standstill for > 72 hours, carrying out disinfection is recom-
mended.