Operating instructions
– LBA4/6/7 – 2017 Version
23
7.2.2
On the rotary base plate:
After carrying out the civil engineering work, you can install the barrier following the procedure below:
A-
Install the anchor plate
B-
Install the housing on the anchor rods taking care not to jam the wires (the stainless steel
sole plate is affixed under the housing in the factory).
C- Install the 4 nylon rotation rings on the anchor rods. They must be positioned on the edge of
the housing.
D- Install the clamping ring.
E-
Install the M16x40 flat washers then the M16 nuts to secure the barrier. Lock the nuts. Check
the rotation. Install and lock the locknuts
F-
The barrier must be earthed using a braid tightened on one of the 4 mounting studs
4 x M16 galvanised
locknuts
4 x M16 galvanised nuts
4 x M16x40 galvanised flat
washers
4 x 16x250 mm anchor
rods
Conduits
C power
loops, etc.
Anchor plate
Stainless steel clamping
ring
4 x Nylon rotation
rings
Stainless steel sliding sole
plate (affixed under the
barrier housing)
A
B
D
C
E