Attaching the roof and casings:
Once the roof has been installed and the casings finished, they need to attached according to the
following procedure:
A-
Install the 4 attachment lugs for holding the roof on the structure (screw head on top)
B-
Install the M6 rounded screw heads for holding the casings on the roof
7.3.4
Installing the access hatches:
Once the entire roof has been installed and attached, you need to install the access hatches according
to the following procedure:
A-
Insert the hatch above the casing
B-
Position the hatch attachment lugs so that they coincide with those of the casing
C- Then, place the hatch horizontally and lock it using the 2 spanners
D- Carry out the same operation for the 2