Step 4
Connect 4 stabilisers to the corners.
Once the stabiliser is postioned
correctly, tighten the 2 couplers -
ensuring the foot of the stabiliser is
firmly on the floo
If building a 3m working platform
height, do not assemble Step 5
below and go to Step 6 on page 13.
Step 5
Remove the platform. Connect two
1m frames together to create a 2m
frame - ensuring that the locking
bolts at the bottom of the upper
frame are engaged. Repeat this for
a 2nd pair of frames. Put a pair of
assembled frames on each end of
the base unit with the head fitting
pointing inwards. Ensure that the
locking bolts at the bottom engage
once added to the base frame.