Step 7
Locate a hanger frame onto the
brace panel as shown. Hang the
toeboard on first, then two brace
panels ready for the next stage.
Step 8
Using the 3T method, add the two
brace panels above the top platform
so the top bar of the brace panel is in
line with the top rungs of the frames.
When the panel is in the correct
position the top hooks will sit just
below the top rung of the frames
and the bottom hook located just
above the 3rd rung down from the
top. Now fit the toeboard
Build Method for 2m Working Platform Height
Step 6
Add a brace panel between rungs 6
and 8 on the same side of the tower
as the folding gate on the base frame.
Make sure that the hooks are facing
outwards. Now, install a platform
onto rung 8 (counting upwards from
the bottom of the tower). Engage
the wind latches at both ends of the
platform.