Page
13
Products |
LEACH'S
Step 6
Remove the platform. Connect a
1m frame on each end of the base
unit with the head fittings pointing
inwards. Ensure that the locking
bolts at the bottom engage once
added to the base frame. Then add
a brace panel between rungs 6 and
8 on the same side of the tower as
the folding gate on the base frame.
Make sure that the hooks are facing
outwards.
Step 7
Add a platform onto the 4th rung
up from the bottom and a second
brace panel between rungs 6 and
8 on the opposite side to the firs
one making sure that the hooks are
facing outwards. Make sure that the
wind latches are engaged on the
platform.
Step 8
Locate a hanger frame on the upper
rungs of each brace panel. Connect
two 1m frames together to create
a 2m frame. Ensure the locking
bolts at the bottom of the upper
frame are fully engaged. Repeat
for a second pair of frames. Hang
one brace panel then two 2m end
frames on one hanger frame. Hang
two brace panels then the toeboard
on the second hanger frame. Hook a
platform onto the end frame.
Build Method for 3m Working Platform Height
Summary of Contents for 1298-IM-EN
Page 19: ...Page 19 Products LEACH S Notes...