Page
15
Products |
LEACH'S
Step 6
Add a brace panel between rungs 6
and 8 on the same side of the tower
as the folding gate on the base frame.
Make sure that the hooks are facing
outwards. Now, install a platform
onto rung 8. Engage the wind latches
at both ends of the platform.
Step 7
Fit a hanger frame onto the brace
panel installed in step 6 and hang
2 brace panels, the toeboard and 2
more brace panels. On the ground
make two 2m frames by connecting
two pairs of 1m frames together.
Now, fit a 2nd hanger frame on one
end of the tower. Hang 1 brace panel
first, then the two 2m frames off it.
Finally hook a platform on the other
end of the tower.
Step 8
Using the 3T method install 2 brace
panels. Remove these from the
hanger on the side of the tower.
Relocate the platform hanging from
the end of the tower round onto the
empty brace panel on the side of the
tower.
Build Method for 4m Working Platform Height
Summary of Contents for 1298-IM-EN