Maintenance 

 
Please  follow  the  preventive  maintenance  programme  listed  below.  This  will  ensure  that  the 
turbine operates reliably and safely with good efficiency. 
 

Always shut down the turbine before attempting to carry out maintenance. 

 

Post-Installation Checks (to be carried out one month after installation): 

 

Check  that  the  turbine  mount  fixings  are  secure  and  has  not  worked  loose.  Adjust  if 
required. 

 

Ensure that the rotor blades rotate freely. 

 

Ensure that all electrical connections are sound. 

 

Annual Maintenance: 

 

Inspect the turbine & support structure. 

 

Ensure that the bearings are smooth and free running. 

 

Inspect  the  rotor  blades  for  damage  such  as  dents  or  chips.  The  blades  will  become 
unbalanced if they are damaged. This will cause vibration, noise and poor performance. If 
many dents have occurred along the edges of the blades, a new set of rotor blades should 
be fitted (part numbers available in the Spares section). 

 

Remove any build-up of dirt and debris from the rotor blades using a mild detergent and 
warm water. 

 

Check the blade fixings for tightness. 

 

Check that all electrical connections are sound and free from corrosion. 

 

Generally  ensure  that  the  turbine  is  in  good  working  condition  and  is  safe  for  continued 
use. 

 

After five years of normal operation: 

 

We recommend that the rotor bearings should be replaced after five years of continuous 

operation. This will ensure that the turbine’s performance and safety is not compromised.

 

 

Other Considerations: 

 

The  equipment  used  in  the  charging  system  (batteries,  charge  controller,  PV  panels, 
invertors,  etc.)  should  be  maintained  according  to  the  instructions  published  by  the 
relevant manufacturer. 

 

Where  lead-acid  batteries  are  used,  it  is  especially  important  that  they  are  maintained 
carefully. Failure to do so will result in the batteries being rendered useless within a short 
period of time. 
 

 
 

 

Summary of Contents for GA-LETU

Page 1: ...ontrilas Hereford HR2 0BW UK www leadingedgepower com Rev K Page 1 of 30 LE v50 LE v50 Extreme Turbine Installation Operation Guide A micro vertical axis turbine for trickle charging and low power app...

Page 2: ...s first 3 Introduction 4 Safety Precautions 5 Specifications 6 Package Contents 7 Tools Required For Assembly 7 Mechanical Assembly Procedure 8 Electrical Installation 11 Turbine Operation 16 Maintena...

Page 3: ...ne to run without being connected to the battery Failing to do so will result in the turbine freewheeling causing premature wear and tear and unnatural blade noise 3 On arrival ensure the main rotor i...

Page 4: ...perating life The LE v50 has been designed to be simple economic durable and yield excellent performance Specific LE v50 turbine features Innovatively designed axial flux alternator using neodymium ir...

Page 5: ...ld be completed at ground level Ensure that the batteries are disconnected during the installation procedure Twist the turbine output cables together to create a short circuit during the mechanical in...

Page 6: ...bine Name LE v50 Part Number GA LETU 010A Turbine Name LE v50 Extreme Part Number GA LETU 020A Rotor Diameter 270 mm Rated Wind Velocity 8 m s Nominal Voltage 12 24V 48V DC Rated Output 12 Watts Cut i...

Page 7: ...ler immediately Tools Required For Assembly You will require the following tools to assemble your LE v50 turbine 13 mm A F spanner 13 mm ratchet one of each required 8mm A F spanner or ratchet A set o...

Page 8: ...e will rotate freely E Retighten the upper and lower stub shaft fixings and check that the turbine still rotates freely F Reposition and fix the cowlings ensuring that they do not rub upon each other...

Page 9: ...om the baseboard it can now be fitted in its intended position The cables should come out of the bottom of the turbine when mounted The LE v50 is supplied as standard with two universal flat mounting...

Page 10: ...ficiency and cost in mind as it is unlikely that your turbine will be running at full capacity 100 of the time If in doubt consult your local electrical supplier The cable should be installed in accor...

Page 11: ...approved conduit trunking Cable strain relief Prevent mechanical strain on the transmission cables running down the tower from the turbine Clip the cables to the inside of the tower Failure to do this...

Page 12: ...Normally the LE v50 turbine does not require any external charge control equipment to be installed in the system Due to the low Tip Speed Ratio of the turbine the turbine output decreases naturally a...

Page 13: ...eford HR2 0BW UK www leadingedgepower com Rev K Page 13 of 30 Fig 4 Simple Stand Alone battery charging wiring diagram LE v50 Turbine Battery Bank wired to the appropriate voltage and capacity VE Tran...

Page 14: ...Tel 44 0 1981 241668 Skyrrid Farm Pontrilas Hereford HR2 0BW UK www leadingedgepower com Rev K Page 14 of 30 Fig 5 Stand Alone battery charging requiring DL 300 controller...

Page 15: ...Tel 44 0 1981 241668 Skyrrid Farm Pontrilas Hereford HR2 0BW UK www leadingedgepower com Rev K Page 15 of 30 Fig 5 Typical Hybrid wind solar system...

Page 16: ...the rotor speed increases so too will the current and voltage Shut Down If Run Stop switch is fitted A run stop switch is not required with the LE v50 turbine but one can be installed if desired see...

Page 17: ...mance If many dents have occurred along the edges of the blades a new set of rotor blades should be fitted part numbers available in the Spares section Remove any build up of dirt and debris from the...

Page 18: ...bine Please contact your nearest Leading Edge Turbines Dealer and quote the part numbers listed below Rotor Blade DP LETU 145 Rotor Bearing Housing DP LETU 198 Bearing Service Kit OS 296 Stator 48VDC...

Page 19: ...e warranty and may compromise the safety of the machine What is not covered by your warranty Damage caused by unsatisfactory installation of the turbine tower and or control equipment Damage caused by...

Page 20: ...nderside of the chassis Disclaimer All specifications are subject to change without prior notice The information given in this user manual is believed to be accurate and reliable Leading Edge Turbines...

Page 21: ...Tel 44 0 1981 241668 Skyrrid Farm Pontrilas Hereford HR2 0BW UK www leadingedgepower com Rev K Page 21 of 30...

Page 22: ...Tel 44 0 1981 241668 Skyrrid Farm Pontrilas Hereford HR2 0BW UK www leadingedgepower com Rev K Page 22 of 30 Appendix 1 DL 300 Charge Controller User Manual...

Page 23: ...plied to the battery and also in relation to the state of charge of the battery The DL 300 Features PWM Pulse Width Modulation for highest charging performance without flicker Selectable three stage c...

Page 24: ...re that the correct size of cable has been selected If a cable of insufficient cross sectional area is used at any point in the electrical system heat will build up in the cables causing a potential f...

Page 25: ...jumper be applied to pins 2 1 position shown to help locate pins 2 2 Use the correct voltage controller A 12V DL 300 controller should only be used on a 12V battery system A 24V DL 300 controller shou...

Page 26: ...he DL 300 and batteries on the positive cable DL 300 Voltage Set Points Whilst operating the DL 300 does a multi stage charge based on time and the bulk and float voltages 12V Set points Mode Flooded...

Page 27: ...Tel 44 0 1981 241668 Skyrrid Farm Pontrilas Hereford HR2 0BW UK www leadingedgepower com Rev K Page 27 of 30 Appendix 2 Run Stop Switch User Manual Only operate in light winds...

Page 28: ...y rotate very slowly Position 2 Turbine Run position The turbine output is allowed to flow straight through the switch Safety Precautions Safety must always be your primary concern during the assembly...

Page 29: ...Universal Run Stop switch is correctly wired as per these instructions and wiring schematics Incorrect wiring may lead to a short circuit being placed across the batteries which can lead to fire or ex...

Page 30: ...s Hereford HR2 0BW UK www leadingedgepower com Rev K Page 30 of 30 Contact Us Your Local Distributor Leading Edge Turbines Ltd Skyrrid Farm Pontrilas Hereford HR2 0BW UK Tel 44 0 1981 241 668 info lea...

Reviews:

Related manuals for GA-LETU