Tel: +44 (0) 1981 241668
Skyrrid Farm, Pontrilas, Hereford. HR2 0BW. UK
www.leadingedgepower.com
Rev K
Page 9 of 30
3)
Remove the turbine from the transit packing
–
Use a pair of 13mm A/F spanner and or
ratchet to remove the M8 fixings from the transit base board.
4)
Fix the turbine in its mounting Position
–
With the turbine removed from the baseboard, it
can now be fitted in its intended position. The cables should come out of the bottom of
the turbine when mounted. The LE-v50 is supplied as standard with two universal flat
mounting brackets. Dimensions of the brackets can be found below. Using U-bolts, the
turbine can be fixed to a 50mm outer diameter pole.
Ensure that the turbine is mounted vertically and on a flat and smooth surface.
Incorrectly mounting the turbine may cause the main spine to distort which may result in
the turbine not rotating freely.