![background image](http://html1.mh-extra.com/html/legrand/0-038-11/0-038-11_manual_1871613012.webp)
12
Installation
Connect the load shedder directly after the electricity sup-
plier circuit-breaker.
1 - Fix it to the switchboard rail.
2 - Connect the phase coming from the circuit-breaker to
the PH terminal.
3 - Connect the circuit-breaker neutral to a distribution ter-
minal strip
4 - Connect one neutral conductor to the N terminal
(1.5 mm
2
).
5 - Connect the priority output (P terminal) to a distribution
terminal strip.
6 - Connect the conductors coming from the terminal strip
above (5) to one of the NP1-NP2-NP3 terminals.
7 - Connect the other NP1-NP2-NP3 terminals to the
devices that have to be load shed.
8 - Set the rating of the load shedder to the same rating as
the electricity supplier circuit-breaker.
Important comments
Check that the power connected to the non priority output is
less than 15 A.
In case of modification to the installation, make sure the
non priority outputs are not overloaded (max. 15 A).