DANGER
All the configurations and start-up operations may only be done by a SKILLED TECHNICIAN (paragraph 2.2.1).
5.1
Introduction
This chapter contains all the information necessary for a correct configuration of the Archimod HE 240-480 HE UPS and
for its subsequent startup.
The factory configuration provides for THREE PHASE INPUT and 120° THREE PHASE OUTPUT.
5.2
Input configuration
The Archimod HE 240-480 automatically recognises the voltage, frequency and number of phases on input. No further
configuration by means of the control panel is therefore necessary.
CAUTION
Make sure the neutral wire is always connected.
5.3
Output configuration
During the start-up, select from the control panel the type of output voltage according to the applied load.
The default configuration for the Archimod HE 240-480 is 120° three phase 400 Vac.
Two different settings can be selected to manage the three phases:
- THREE PHASES 120°: this is the default setting and is usually used if three phase loads are applied on the UPS output
(e.g. three phase electrical motors) or if there are both three phase and single phase loads. The UPS manages the three
output phases protecting the three phase load. For example, if an excessive load is applied to one of the three output
lines, the automatic bypass switches all three lines on output.
- THREE SINGLE PHASE OUTPUTS: this setting is necessary if three single phase output lines with the neutral in common
have been created. The UPS manages the three outputs completely independently of each other. For example, if an
excessive load is applied to one of the three output lines, the bypass only cuts in on the overloaded line while the power
supply continues to be guaranteed on the other two by the UPS.
For the correct selection of the output configuration, follow the instructions given in paragraph 5.5.
5.4
Pre-start-up checks
Before powering the equipment, carry out the following checks:
1. Check that the mains input disconnector of the UPS is open (OFF position).
2. Check that the bypass input disconnector of the UPS is open (OFF position).
3. Check that the battery disconnectors of the external battery units are open.
4. Check that the maintenance bypass disconnector and the output disconnectors of the UPS are open (OFF position).
5. Check that the input and output wiring has been done and that all the connections have been tightened up properly.
6. Check the correct phase sequence of the mains input and bypass line (if separate).
7. Check that the parameters (voltage and frequency) of the mains input are compatible with those shown on the UPS
rating plate.
8. Check that all the power modules are inserted properly and that the fixing screws of the power modules are present
and screwed up to abut the relative slots (use SHC M4x20 screws with hex socket head).
5. Configuration and Start-up
Summary of Contents for Archimod HE 240
Page 1: ...Archimod HE 240 480 Installation and maintenance manual Item LE09392AA 12 16 01 CT ...
Page 2: ...2 EN ENGLISH 3 Archimod HE 240 480 ...
Page 14: ...14 3 Models ...
Page 15: ...Archimod HE 240 480 Installation and maintenance manual 15 Block diagram ...
Page 18: ...18 3 Models ...
Page 19: ...Archimod HE 240 480 Installation and maintenance manual 19 Block diagram ...
Page 23: ...Archimod HE 240 480 Installation and maintenance manual 23 ...
Page 24: ...24 4 Installation ...
Page 25: ...Archimod HE 240 480 Installation and maintenance manual 25 ...
Page 26: ...26 4 Installation ...
Page 27: ...Archimod HE 240 480 Installation and maintenance manual 27 ...
Page 28: ...28 4 Installation ...
Page 33: ...Archimod HE 240 480 Installation and maintenance manual 33 Archimod HE 240 ...
Page 36: ...36 Archimod HE 240 4 Installation ...
Page 41: ...Archimod HE 240 480 Installation and maintenance manual 41 Archimod HE 240 ...
Page 70: ...70 ...
Page 71: ...Archimod HE 240 480 Installation and maintenance manual 71 ...