6
Connecting Mounting Uprights
1.
Use four 10-24 x 1/2" flathead Phillips screws (Q) to secure
spacer plates (P) to mounting uprights (L and M or M and
M). (See Figure 2) or (See Figure 3)
IMPORTANT ! :
If installing from left to right, first attach
left upright (L) to middle upright (M). If installing from the
middle out, first attach two middle uprights (M) to each
other.
Figure 2
Figure 3
Preparing LED Screens
1.
Attach four mounting buttons (L) per LED screen, one to
each corner of LED screen, with four M5 x 20mm Phillips flat
head screws (K). (See Figure 4)
Figure 4
Determining Installation Site
IMPORTANT ! :
The top of the LED screen is 5.25" above
the center line of the mounting lags in the upper mounting
slots. (See Figure 5)
IMPORTANT ! :
The bottom of the LED screen is 6.5"
below the center line of the mounting lags in the lowest
mounting slots.
NOTE:
Refer to dimensions drawings on pages 16-19 for
further details on installation locations
NOTE:
If desired, the mount installation may be started in the
middle of the video wall, attaching mounts out from the
center to the left and right ends. Installation on smaller
walls may be easier if started at the left side of the video
wall using the following instructions.
1.
Determine location for the
top left
corner of the LED wall.
(See Figure 5)
2.
Make a mark 5.25" below the planned top left corner of the
LED wall. (See Figure 5)
3.
Using a level, mark a horizontal line across width of LED
wall from the mark made in Step 2.
NOTE:
This line will indicate the center line for the location of the
mounting lags in the mounting slots for the top mount(s)
in the video wall. The oversize mounting slots will allow
some upward adjustment as needed. (See Figure 5) and
(See Figure 6)
1
(Q) x 4
(P)
(L)
(M)
(TILD1X05US shown - left to right)
1
(Q) x 4
(P)
(M) x 2
(TILD1X05US shown - from middle out)
LED screen
1
(K)
[TILD1X05 shown as example]