Tools Required for Installation
1. Hang case and attach to support structure with bolts. See
Suggested Methods of Installation.
2. Tighten bolts until trim flange is flush with ceiling.
NOTE:
For proper operation, case must be levelled side to
side and front to back.
3. Remove 2 screws to open junction box. Install electrical
connections that apply to your unit. Make sure to review the
wiring diagram for proper hook up. Replace junction box
cover and secure with 2 screws.
NOTE:
Must be installed in accordance with the requirements
of the Local Building Codes, the Canadian Electrical Code
(CEC), CAN/CSA C22.1 and the National Electric Code (NEC),
NFPA 70.
Case Installation
Pre-Installation
1. Carefully unpack case from shipping carton.
2. Set aside the Installation Kit. Items inside will be used
during installation.
3. Make sure to recheck measurement of case for proper
installation clearance.
4. Remove any protective foam covering the outside
of the case.
1/2“ and 5/16" Open Wrench
or Socket Driver
1/8” Hex Key
(included)
5. For shipping purposes, foam is also inserted between the
roller brackets and end caps (Figure 1). Remove these foam
blocks from the ends.
6. Remove the hanger brackets from the top of the case
using a 1/2" wrench. Do not discard the hardware; it will be
used during case installation to re-attach the hanger
brackets for mounting.
If your case was ordered in advance of the screen and
roller assembly, your installation is now complete.
Continue to step 4 if your Tensioned Advantage Electrol
was ordered as a complete unit.
4. Use a 5/16" socket or wrench and the supplied 1/8" hex key to
remove silver shipping brackets attached to slat and screen
case.
5. Test installation by running screen up and down a few times.
Be prepared to stop screen should any objects obstruct the
movement of the screen. To prevent damage to the motor,
the standard duty cycle is 1 minute on and 3 minutes off.