59
KEOR T
Oper
ating M
anual
THREE PARALLEL UNITS N+1 Redundant Configuration with Single Distribution Input (5-30kVA)
a1, a2, a3:
Mains Supply MCCB 4p
d:
Distribution MCCB
o1, o2, o3
unit output switch 4p
OS:
General output switch 4p
Q:
External Maintenance Bypass MCCB 4p
NOTE:
Q =
External Maintenance By pass MCCB
OS =
general output disconnect switch
Rating = N X unit rating (kVA)
Internal Maintenance Bypass Q3 cannot be used should be locked to avoid any misuse.
Option
o1, o2, o3=
unit output disconnect switch to enable single unit complete shut down for maintenance
a, o, OS, Q
should be 4poles unless TN-C distribution is used
In case we have parallel system with internal transformer; it is recommended to install output switches (o) to
enable sequential energizing of the different transformers.
Summary of Contents for Keor T 10KVA
Page 1: ...LE10795AB KEOR T 208V 5 60 KVA Operating Manual ...
Page 4: ...KEOR T ...
Page 53: ...49 KEOR T Operating Manual SEPARATED RECTIFIER AND BYPASS INPUTS FOR SINGLE UPS UNIT 5 30kVA ...
Page 54: ...50 SEPARATED RECTIFIER AND BYPASS INPUTS FOR SINGLE UPS UNIT 40 60kVA ...
Page 55: ...51 KEOR T Operating Manual COMMON RECTIFIER AND BYPASS INPUTS FOR SINGLE UPS UNIT 5 30kVA ...
Page 56: ...52 COMMON RECTIFIER AND BYPASS INPUTS FOR SINGLE UPS UNIT 40 60kVA ...