3.7 POWER CABLE CONNECT
Once the equipment has been finally positioned and secured, connect the power cables as
described in the following procedure.
Verify the UPS is totally isolated from its external power source and all power isolators of
the UPS are open. Check to see if they are electrically isolated and post any necessary war-
ning signs to prevent their inadvertent operation.
Remove the cover of terminals for wiring easily.
Terminal sequence from left to right: Input phase A(L1), input phase B(L2), input
phase C(L3), input Neutral line, Output phase A(L1), Output phase B(L2), Output phase
C(L3), Output Neutral line, There are 3 connectors of GROUND under the terminal block.
Choose appropriate power cable. (Refer to the table above) and pay attention to
the diameter of the connection terminal of the cable that should be greater than or equal to
that of the connection poles;
10 kVA
20 kVA