DELTA
Installation Manual
Edition July 2013
DELT
∆
∆
∆
∆
platform lift
page 2 of 24
Observe the following points before installation!
Installation teams must have a general knowledge in:
•
working on electric controls
•
basic mechanical engineering and providing adequate fixation of the rails and pillars
•
reading and understanding circuit diagrams and wiring schematics
The following points are necessary for the installation:
•
Have a complete tool kit on hand for mechanical and electrical works
•
Check beforehand what fixing materials (screws, anchor bolts, adhesives) are
required for the proper fixing of the rails to the wall or the pillars to the floor. These
materials are not included in the delivery! The installation company is responsible
for the fixing of the rail to the wall or the pillars to the floor/steps!
•
Check the packages for shipping damage and missing parts before bringing the lift
to the site. Take pictures of damaged parts as soon as these are discovered to
provide proof for warranty claims.
•
A team of 2 qualified technicians is necessary to install the lift.
Bring the platform to the upper landing before fixing the rails in order to prevent damage to
the rail and platform during transport on the staircase! The platform can only be engaged
from the upper end of the rail.
Caution:
The large platform is heavy; it weighs approximately 120 kg. A dolly might be
necessary to transport the platform up the steps.
The following tools will be required to finish the installation successfully:
A complete toolset for
mechanical and electrical works
Voltmeter
Drilling machines
Drills, thread cutter
Fixing material
Water lever with angle
indication