19
Rugby 200-3.2.1en
Calibration
Checking “Laydown”
Calibration
1 To check laydown calibration, place
the Rugby 200 on its side on a flat
level surface 100 ft (30 m) from a
wall so that the rotating beam
projects a line on the wall.
2 Hang a plumb line on the wall.
3 If the rotating beam is not plumb,
adjustment is necessary.
Rugby200-20 200 laydown.eps
1) Scan Area
2) Plumb Line
Adjusting “Laydown”
Calibration
1 With the Rugby still in laydown
position, enter calibration mode the
same as described for upright cali-
bration (steps 1–3)
2 Have the rotating beam scan the
plumb line, then use the Up and
Down Arrow Buttons to align the
beam vertically.
)
Using the IR Remote will allow
calibration to be adjusted remotely
while closely monitoring the beam at
the plumb line.
3 Once desired calibration is
achieved, press the Power Button
on the Rugby once to store the
information and turn the power off.
The Rugby will be set to the new
calibration when power is re-
applied.