20.0 Responsibilities
This procedure is to be performed by a Leidos field service representative.
21.0 Installation Overview
This appendix explains how to install the Provision 3 Vibration Control Kit on a Provision AIT-2. This
instruction assumes that the scanner is powered off and the Lock Out-Tag Out procedures have been
followed.
21.1
Installation Sequence
Installing the Provision 3 V
ibration Control Kit requires the masts to be in the ‘calibration position’. The
Leidos technician should place the masts in that configuration prior to power down.
1.
Remove the required components to access the inner end cap panels.
2.
There are two methods for determining how to locate the foam block on the endcaps.
21.2
Method 1
1.
In the vibration kit (1600-21348-00), locate the white mylar template (3000-22607-00).
2.
Clean the area that the foam block adheres to with alcohol.
3.
Position the template (as shown in the following figureFigure 101) and mark the position for the
foam.
4.
Repeat this process for the four endcaps.
Figure 101: Using Template to the Locate Foam Block