B4 Fan Motor Test Procedure
A simple test can be used to test the fan motor operation. A fully charged 9V battery will be required for this procedure.
J2
F
A
N
PWM OUT
P
ARK
COM
BLACK LEAD
BROWN LEAD
BROWN LEAD
BLACK LEAD
REMOVE BOTH LEADS
FROM J2 TERMINALS
CONNECT B4 FAN MOTOR BLACK
COMMON WIRE TO 9V BATTERY
NEGATIVE TERMINAL
A177 FAN MOTOR CONTROL
BLACK LEAD
BROWN LEAD
B4 FAN MOTOR TEST
FULLY CHARGED 9V BATTERY
This is a test that will verify that the motor does operate.
J2
1. Verify main (240 volt) power if
OFF
to unit.
2. Remove both wires (brown and black) from the J2 terminal on the A177 fan
motor control.
3. Room thermostat should be in
OFF
position (unit in idle mode − no heating or
cooling demands)
4. Turn main power (240 volt)
ON
to unit.
5. Connect 9 Volt battery to B4 fan motor plugs as noted in picture
below.
6. B4 fan motor should run at a reduced fan speed.
7. If B4 fan motor does not run, then replace fan motor assembly.
NEGATIVE TERMINAL
POSITIVE TERMINAL
CONNECT B4 FAN MOTOR WIRE
TO 9V BATTERY POSITIVE
TERMINAL
V
Figure 26. B4 Fan Motor Test
Summary of Contents for XC21
Page 21: ...Page 21 XC21 SERIES Figure 8 Typical XC21 Wiring ...
Page 39: ...Page 39 XC21 SERIES Figure 19 High Pressure Switch Operation ...
Page 40: ...Page 40 506518 01 Figure 20 Low Pressure Switch Operation ...
Page 41: ...Page 41 XC21 SERIES Figure 21 High Discharge Temperature Sensor Operation ...