Outlet 10 2 Sec
Outlet 11 5 Sec
Outlet 12 3 Sec
The following table shows the PDU outlet power-on timing when power is restored after a power outage.
Table 3. Power-on timing
Outlet
number
Outlet power-on
timing
Comment
1
16th second
Total Delay time =bootup time + GlobalDela IndividualDelayTimer
2
17th second
Total Delay time =bootup time + GlobalDela IndividualDelayTimer
3
18th second
Total Delay time =bootup time + GlobalDela IndividualDelayTimer
4
Off
Previous state is Off
5
17th second
Total Delay time = bootup time + GlobalDela IndividualDelayTimer
6
17th second
Total Delay time = bootup time + GlobalDela IndividualDelayTimer
7
19th second
Total Delay time = bootup time + GlobalDela IndividualDelayTimer
8
16th second
Total Delay time = bootup time + GlobalDela IndividualDelayTimer
9
17th second
Total Delay time = bootup time + GlobalDela IndividualDelayTimer
10
Off
Previous state is Off
11
20th second
Total Delay time = bootup time + GlobalDela IndividualDelayTimer
12
Off
Previous state is Off
The following sections explain how to configure the GlobalDelayTimer and IndividualDelayTimer parameters
through the serial port (by using HyperTerminal or similar applications) or through the Ethernet port (by using
Telnet and SNMP).
Using HyperTerminal through the serial port
To set the parameters for the power-on sequence function by using a serial port (HyperTerminal interface),
complete the following steps:
Step 1. Make sure that the serial port configuration is 115200, 8-N-1-None.
Step 2. Log-in as ADMIN/1001.
Chapter 5
.
Monitoring the power status
33
Summary of Contents for 46M4002
Page 1: ...1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 24: ...16 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 30: ...22 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 34: ...26 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 56: ...48 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 60: ...52 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 62: ...54 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 68: ...60 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 70: ...62 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 74: ...66 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Page 85: ......
Page 86: ......