4 - COMMISSIONING

 

BEFORE INSTALLATION

 

If the equipment has been stored for several months, it is
essential to check the following:
- the cleanliness of the interior and that there is no
condensation
- correct insulation between the phases and the earth terminal
on the motor (minimum 100M

 

 

 at 500 V D.C. for 60 seconds)

after having disconnected all the electronic circuits if
necessary.

 

WARNING:

 

 do not apply the megohmmeter to the terminals

of the thermal sensors as this may damage them.

If the required value is not reached, dry using internal or
external heating.

 

Drying using external heating

 

- place the motor in an oven at 70°C for at least 24 hours until
the correct insulation is achieved. (100M

 

 

)

- Take care to increase the temperature gradually to clear the
condensation.
- After drying, during the cooling phase, check the insulation
value regularly, as it will initially tend to fall then rise.

 

Drying using internal heating

 

- Test to be carried out with the brakes released.
- Connect motor windings V and W in parallel in relation to U.
(see drawing below)
- Read off the resistance between U and V//W.
- Apply a 

 

low voltage

 

 D.C. current to them (to obtain 10% of

the rated current calculated using the resistances of the
winding), increase the voltage until 50% of the rated current
is reached. 
- Maintain the power for 4 hours. The temperature of the
motor should increase slightly.

 

CAUTION: The pulley will move slightly on power-
up (angular setting of the rotor in relation to the

stator).

 

4.1 - INSTALLATION

 

The installation must comply with the characteristics of the
motor indicated on the nameplate (see section 1).
It must include electrical safety devices.
Check that the handling equipment (slings, etc.) are suitable
for the weight of the machine.  
Use the attachment points provided on the machine.
Check that the cables are correctly positioned so that they are
not damaged.
Provide the necessary mechanical protection devices to
prevent people working on the machine becoming caught or
trapped by the pulley and/or the cables.
The motors must be installed in such a way that the cooling
air (not too damp, dust-free, and containing no vapour or
corrosive gas) circulates freely. 

 

4.1.1 - Cleaning

 

- Release the brake using the manual release system.
- Remove the protective varnish from the pulley grooves.

 

CAUTION: Do not use abrasive equipment. Use
only a cloth soaked in alcohol. Care must be taken

not to get any alcohol or grease on the brake disk.

WARNING:

 

 use the alcohol in a well ventilated area.

 

Z2-Z3 Fabricated steel shield

 

Motor connection for drying the winding

 

Phase connection

Power supply (-)

U

Power supply (+)

V + W (serial)

Anchoring points 

for lifting

Fixing screws

Summary of Contents for GEARLESS Z2

Page 1: ...This manual is to be given to the end user GEARLESS Z2 Z3 A C drive for elevators Installation and maintenance 3862 en 07 2004 a...

Page 2: ...performing any work on the motor or the brakes The magnetic field on the rotor may affect pacemakers The motor rotor contains a powerful magnetic field This field may affect digital devices such as w...

Page 3: ...e released by the manual release system In certain transport conditions the grooves of the driving pulley are protected by a special varnish This varnish must not be removed during storage 2 2 Prolong...

Page 4: ...lated using the resistances of the winding increase the voltage until 50 of the rated current is reached Maintain the power for 4 hours The temperature of the motor should increase slightly CAUTION Th...

Page 5: ...of thermal sensor cable 2 m Fig 2 Motor connection Brake wiring Continuous supply see name plate Connect the motor using cables of the correct cross section the cables and tags must be sized according...

Page 6: ...ned After starting up check noise vibration operation of the buttons switches also check the current and voltage on the machine while it is operating with the rated load Encoder wiring refer to the da...

Page 7: ...no rattling and ensure that the pulley rotates freely with the brakes released If there is too much noise re adjust the brake using 0 20 mm shims 3 After this operation it is essential to check the ad...

Page 8: ...or each spare part Name and or reference number of the part quantity ordered For instant identification please give the reference of the document used for the order drawing number or manual The type a...

Page 9: ...9 INSTALLATION AND MAINTENANCE GEARLESS Z2 Z3 A C Drive for elevators LEROY SOMER 3862 en 07 2004 a...

Page 10: ...10 INSTALLATION AND MAINTENANCE GEARLESS Z2 Z3 A C Drive for elevators LEROY SOMER 3862 en 07 2004 a...

Page 11: ......

Page 12: ...LEROY SOMER 16015 ANGOUL ME CEDEX FRANCE RCS ANGOUL ME N B 671 820 223 S A au capital de 62 779 000 www leroy somer com...

Reviews: