Page 7 of 11
PK-A3188-10-00-0B
CABLE INSTALLATION
1) Feed incoming cable(s) through the grommet opening.
2) Optional – Install Universal Trunk Clamp kit and secure cable to clamp.
3) Remove required outer cable jacket leaving jacket at the closest lance point.
4) Secure the cable to the lance point with Velcro or nylon tie wraps as appropriate.
5) If applicable, secure aramid yarn to lance point.
6) When using Armored cable, secure the ground wire from the armored cable to the provided grounding lug or
ground by other code compliant methods to the provided grounding stud.
7) Using the cable management saddles, route the breakout fiber legs to the patching or termination point as shown
in the configuration drawings below: (Figures 4 to 11)
ROUTING FOR FIELD AND PRE-TERMINATED TERMINATION –
(SMALL/MEDIUM ENCLOSURES)
ROUTING FOR FIELD TERMINATED CABLING – SPLICE MODULES
Figure 4
Figure 5