Installation
51
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
J
To make an electrical connection between the Home 8 and SE Box, installing the required
ampacity circuit breakers on the SE Box is required. (40A breaker is required.)
Install a 40A circuit breaker in the Home 8 as shown in the following figure.
K
On the SE Box side, connect the AC conductors to the corresponding terminals as shown in
the figure.
L1 (Black)
L2 (Red)
N (White)
G (Green)
From Home 8
Flat head screwdriver
Depending on wire size.
Follow the guide from
the Eaton BR series.
Flat head screwdriver
2-2/0 AWG –
58 kgf·cm (50 lbf·in) torque
6-4 AWG –
52 kgf·cm (45 lbf·in) torque
14-8 AWG –
40 kgf·cm (35 lbf·in) torque
Before inserting the cable conductors to the terminals, loosen the screw and then fix the
screws tightly. Shake the cable to check the connection status.
CAUTION