Selecting the location
• When the Chiller is installed in the vicinity of fire: Keep the distance more than 5 meters away from boilers, hot-air
blowers, and more than 2 meters away from other heating devices.
• Avoid the places of high temperature and choose a well-ventilated place.
• Choose a place with low moisture
• Secure the service area (for operation, plumbing maintenance, and tubes maintenance).
Foundation
• Build the foundation to withstand the concentrated load of the chiller.
• The foundation level should be higher than the surface level of the water, and install the drain plumbing around.
• Install the drain plumbing in the sewer.
Delivery installation
• Deliver the Chiller horizontally as far as possible.
• The installation order : Place isolation pad on the base board, keeping the horizontality within ±1mm, and then in-
stall the Chiller.
• Lastly, confirm that the horizontality is within ±1mm using a level. If not, readjust it within ±1mm, using spacers.