Minimum distances
1. Side vertical wall
2. Floor
a. Distance between fire dampers installed within vertical wall
b. Distance between fire damper and vertical lateral wall / floor
c. Distance between fire dampers installed within floor
d. Distance between fire damper and vertical lateral wall
Fire dampers installed within vertical wall
Fire dampers installed within floor
Installation
a [mm]
b [mm]
c [mm]
d [mm]
Rigid w
all
EI 120 S Installation within vertical rigid wall
Mortar or plaster putty sealing
50
75
-
-
EI 90 S Installation within vertical rigid wall
Plasterboard and rock wool 100 kg/m³ sealing
50
75
-
-
Fle
xible w
all
EI 120 S Installation within vertical light wall (plasterboard)
Mortar or plaster putty sealing
50
75
-
-
EI 90 S Installation within vertical light wall (plasterboard)
Plasterboard and rock wool 100 kg/m³ sealing
50
75
-
-
EI 60 S Installation within vertical light wall (plasterboard)
Plasterboard and rock wool 80 kg/m³ sealing
50
75
-
-
EI 120 S Installation within vertical light wall (gypsum
blocks wall)
Plaster putty sealing
50
75
-
-
EI 90 S Installation within vertical light wall (gypsum blocks
wall)
Plaster putty sealing
50
75
-
-
Floor
EI 120 S Installation within floor
Mortar sealing
-
-
50
75
EI 90 S Installation within floor
Mortar sealing
-
-
50
75