2-94
Removal and Installation
January 24, 2017
Removal and installation of radiator
CLG835H
Installation
15. Uplift the traveling crane, lift
out the radiator assembly
slowly and put it on flat
ground.
Tool:
Traveling crane
Graph
Contents
Tools
P18P00163
Graph
Contents
Tools
1. Uplift the traveling crane, lift
the radiator assembly to
installing position.
Tool:
Traveling crane
Wire rope
2. Tighten the radiator mount-
ing bolts with the tightening
torque 305
±
25N.m.
Tool:
Open-end
wrench 24#
P18P00164
P18P00165
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...