4-150
Removal and Installation
January 24, 2017
Work hydraulic system
CLG835H
Removal and installation of control valve
Removal of control valve
Removal steps:
Figures
Operation instruction
Tools
Before removing, release
system pressure, support the
boom firmly and fix the bucket
1. Screw off the 4 fastening
bolts of the cover plate at
the access port of the con-
trol valve of the front frame
and remove the cover plate;
Open-end
wrench: 10mm
2. Mark the symbols: "X1-
boom big cavity linkage
pilot", "X2-boom small cavity
linkage pilot", "X3-bucket big
cavity linkage pilot", "X4-
bucket small cavity linkage
pilot" , "X5-multi-functional
big cavity linkage pilot", "X6-
multi-functional small cavity
linkage pilot" respectively on
the pilot hose connected to
the control valve; the marks
shall be firm.
3. Remove these 6 hoses
together; mask oil ports;
Open-end
wrench: 19mm
P18H00211
P18H00212
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...