7-6
Structure Function Principle
January 24, 2017
Work implement
CLG835H
Work implement
The parameters of work implement
Overview and configuration scheme of work implement system
Work implement is a reverse six-link mechanism, which is critical part for the whole loader to finish the
motions of loading, transportation, discharge, etc., the bucket is installed on the front end of work
implement, and the rear end is connected with front frame by the pin.
Items
Standard boom+1.9
square quick cou-
pler bucket
Standard
boom+general
bucket of 1.9 cubic
meters
Extension boom
+1.9 square quick
coupler bucket
Extension
boom+general
bucket of 1.9 cubic
meters
Dumping height
2650mm/ 104in
2762mm/ 108in
2930mm/ 115 in
3043mm/ 120in
Dumping reach
1150mm/ 45in
1050mm/ 41in
1157mm/ 45in
1058mm/ 42in
Breakout force of the
bucket
85KN/ 19kips
100KN/ 22kips
83KN/ 18kips
98KN/ 22kips
Breakout force of the
boom
71KN/ 16kips
78KN/ 17kips
64KN/ 14kips
70KN/ 16kips
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...