4-86
Testing and Adjustment
January 24, 2017
Pressure test of work hydraulic system
CLG835H
Pressure inspection and adjustment of overload valve of bucket tilting small cham-
ber
1. Test method
Figures
Operation instruction
Tools
1. Remove the plug, install the
pressure measuring connec-
tor 30C3280; connect the
pressure gauge at pressure
measuring point;
Pressure gauge
(range 40MPa\
5800psi);
2. Start the machine, operate
the lever to lift boom to hori-
zontal position (when the
diesel engine and hydraulic
oil is under normal operating
temperature, the diesel
engine will be in idle run-
ning)
P18H00084
P18H00085
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...