7-34
Removal and Installation
January 24, 2017
Removal and installation of work implement system
CLG835H
Removal and installation of accessory system
Removal and installation of bucket
Bucket removal
Figures
Operation instruction
Tools
1. Remove linkage front pin
1) Start the machine, put the
boom in the lowest position;
lay flat the bucket and then
switch off.
2) Disassemble the captive
bolt of linkage front pin.
18# Wrench
P18S00054
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...