Applicators:
Select a suitable pure bristle type paint brush.
Use a proper width brush or roller to apply the
primer and cement (see chart below). Speedy
application of cement is important due to its fast
drying characteristics. IMPORTANT NOTE: A
dauber type applicator should only be used on
pipe sizes 2” and below. For larger diameter pipe,
a brush or roller must be used.
RECOMMENDED BRUSH* SIZE FOR
PRIMER AND CEMENT APPLICATIONS
Nominal
Pipe (IPS)
Brush Size
3
1.5” - 2.5”
*USE ONLY NATURAL BRISTLE
Table 3.
3. MAKING THE JOINT
A. Cutting
Pipe must be squarely cut to allow for the proper
interfacing of the pipe end and the fitting socket
bottom. This can be accomplished with a miter box
saw or wheel type cutter. Wheel type cutters are
not generally recommended for larger diameters
since they tend to flare the corner of the pipe end.
If this type of cutter is used, the flare on the end
must be completely removed.
Note:
Power saws, if used, should be specifically
designed to cut plastic pipe.
Figure 41.
B. Deburring
Use a knife, plastic pipe deburring tool, or file to
remove burrs from the end of small diameter pipe.
Be sure to remove all burrs from around the inside
as well as the outside of the pipe. A slight chamfer
(bevel) of about 10°-15° should be added to the
end to permit easier insertion of the pipe into the
end of the fitting. Failure to chamfer the edge of the
pipe may remove cement from the fitting socket,
causing the joint to leak.
Figure 42.
C. Test dry fit of the joint
Tapered fitting sockets are designed so that
an interfaced fit should occur when the pipe is
inserted about 1/3 to 2/3 of the way into the socket.
Occasionally, when pipe fitting dimensions are at
the tolerance extremes, it will be possible to fully
insert dry pipe to the bottom of the fitting socket.
When this happens, a sufficient quantity of cement
must be applied to the joint to fill the gap between
the pipe and fitting. The gap must be filled to obtain
a strong, leak-free joint.
D. Inspection, cleaning, priming
Visually inspect the inside of the pipe and fitting
sockets and remove all dirt, grease or moisture
with a clean dry rag. If wiping fails to clean the
surfaces, a chemical cleaner must be used. Check
for possible damage such as splits or cracks and
replace if necessary.
Depth-of-entry
Marking the depth of entry is a way to check if the
pipe has reached the bottom of the fitting socket
in Step F. Measure the fitting depth and mark this
distance on the pipe O.D. You may want to add
several inches to the distance and make a second
mark as the primer and cement will most likely
destroy your first one.
Apply primer to the surface of the pipe and fitting
socket with a natural bristle brush. This process
softens and prepares the PVC or CPVC for the
solvent cementing step. Move quickly and without
hesitation to the cementing procedure while the