©2021 Lowell Manufacturing Co. | X-Rev.10-21-21
15
Step 6: Now, it is possible to put the batteries inside following the picture below (in the following drawing is
indicated the fasten positions for the correct batteries placing).
Note:
To install the second string of batteries, repeat the same procedure on the right side of battery box.
Step 7: Connecting all batteries following the wiring diagram shown in chapter 5.
Step 8: Secure all batteries inside with the metal plate.
Note:
To install the second string of batteries, repeat the same procedure on the right side of battery box.
Step 9: Put metal top cover back to the unit. Close the frontal fixing plate and the two parts of the front
panel and secure it with screws.
Step 10: Connect the battery box to the UPS.