Cable ED-3T053-40, G5 to Power Switch
Disk power cable to Disk Module
Fan power cable to fan
-48 V input power cable ED-3T053-15, G17.
12.
Referring to Figure 10.24-5 , remove the four screws holding the Power Supply (CGG2) to the power board
bracket.
13.
Place the new Power Supply on the power board bracket and replace the four screws.
14.
Install the following cables to the connectors on the Power Supply:
Cable ED-3T053-40, G5 to Power Switch
Disk power cable to Disk Module
Fan power cable to fan
-48 V input power cable ED-3T053-15, G17.
15.
Go to Step 31 and install DUP cover.
16.
To replace the Power Switch (CGG1), at the Power Supply, remove the following cables from connectors on
the Power Supply:
Cable ED-3T053-40, G5 to Power Switch
Disk power cable to Disk Module
Fan power cable to fan
-48 V input power cable ED-3T053-15, G17.
17.
At the Power Switch, remove the scan/alarm cable ED-3T053-40, G5 and G6 from the Power Switch
connector.
18.
Referring to Figure 10.24-5 , from underneath the DUP chassis, release the locking tab and push the power
board bracket back (to the rear of the DUP) to disengage the mounting tabs. Remove the power board
bracket from the DUP chassis.
19.
Remove the four screws holding the Power Supply (CGG2) to the power board bracket and remove the
Power Supply.
20.
Remove the four screws holding the Power Switch (CGG1) to the power board bracket and slide the Power
Switch out of the bracket.
21.
Slide the replacement Power Switch (CGG1) into the power board bracket and secure with four screws.
22.
Mount the Power Supply (CGG2) on the power board bracket and secure with four screws.
23.
Slide the power board bracket with both units mounted onto the chassis to engage the mounting tabs. Ensure
that the locking tab is also engaged.
235-105-210
October 1999
Copyright © 1999
Page 7
Summary of Contents for 5ESS-2000
Page 96: ...235 105 210 October 1999 Copyright 1999 Page 2 ...
Page 184: ...235 105 210 October 1999 Copyright 1999 Page 3 ...
Page 300: ...13 STOP YOU HAVE COMPLETED THIS PROCEDURE 235 105 210 October 1999 Copyright 1999 Page 55 ...
Page 339: ...7 STOP YOU HAVE COMPLETED THIS PROCEDURE 235 105 210 October 1999 Copyright 1999 Page 13 ...
Page 342: ...235 105 210 October 1999 Copyright 1999 Page 2 ...
Page 359: ...235 105 210 October 1999 Copyright 1999 Page 5 ...
Page 609: ...2 STOP YOU HAVE COMPLETED THIS PROCEDURE 235 105 210 October 1999 Copyright 1999 Page 12 ...
Page 676: ...235 105 210 October 1999 Copyright 1999 Page 9 ...
Page 792: ...3 STOP YOU HAVE COMPLETED THIS PROCEDURE 235 105 210 October 1999 Copyright 1999 Page 9 ...
Page 799: ...Figure 11 36 3 1 Cleaning Points 235 105 210 October 1999 Copyright 1999 Page 7 ...
Page 801: ...235 105 210 October 1999 Copyright 1999 Page 9 ...
Page 839: ...2 STOP YOU HAVE COMPLETED THIS PROCEDURE 235 105 210 October 1999 Copyright 1999 Page 16 ...
Page 999: ...2 STOP YOU HAVE COMPLETED THIS PROCEDURE 235 105 210 October 1999 Copyright 1999 Page 13 ...
Page 1008: ...Figure 11 55 1 CTSNS DIP Switch Settings 235 105 210 October 1999 Copyright 1999 Page 2 ...
Page 1011: ...235 105 210 October 1999 Copyright 1999 Page 5 ...
Page 1053: ...235 105 210 October 1999 Copyright 1999 Page 15 ...
Page 1289: ...Figure 15 17 2 AMATPS Data Link 235 105 210 October 1999 Copyright 1999 Page 2 ...
Page 1292: ...235 105 210 October 1999 Copyright 1999 Page 5 ...
Page 1303: ...9 STOP YOU HAVE COMPLETED THIS PROCEDURE 235 105 210 October 1999 Copyright 1999 Page 2 ...
Page 1360: ...Figure 15 47 2 Typical SCANS III Link Diagram 235 105 210 October 1999 Copyright 1999 Page 2 ...
Page 1372: ...235 105 210 October 1999 Copyright 1999 Page 2 ...
Page 1374: ...235 105 210 October 1999 Copyright 1999 Page 4 ...
Page 1421: ...Table 1 1 O M Checklist 235 105 210 October 1999 Copyright 1999 Page 3 ...