Issue 9 October 1998 8-1
Lucent Technologies
8
Releases 9 and 11 Installation Tests
Overview
This section provides test procedures for verifying the following on Releases 9 and
11 configured DDM-2000 OC-3 shelves:
■
Shelf transmission
■
Wiring to DS1 Cross-Connect (DSX-1)
■
Wiring to DS3/EC-1 Cross-Connect (DSX-3) or DACS IV 2000
■
Fiber Installation and System Test.
Description
The following information provides instructions on the use of an American
Standard Code for Information Interchange (ASCII) terminal and the suggested
installation tests which should be performed. If problems are encountered, refer to
the "Troubleshooting" section at the end of this manual. For detailed
troubleshooting, refer to 363-206-280,
DDM-2000 OC-3 Multiplexer User/Service
Manual
.
The installation tests verify transmission through the shelf, wiring to the cross-
connect (or DACS IV 2000), fiber installation and end-to-end transmission as
shown in Figure 8-1.
The following installation tests are run only in an out-of-service mode of operation.
Interruption of service will result if these tests are run on an operating in-service
system.
Summary of Contents for DDM-2000 OC-3
Page 4: ...Issue 9 October 1998 363 206 204 Lucent Technologies ...
Page 9: ...363 206 204 Issue 9 October 1998 Lucent Technologies ...
Page 10: ...Issue 9 October 1998 363 206 204 Lucent Technologies ...
Page 24: ...xxiv Issue 9 October 1998 363 206 204 ...
Page 32: ...xxxii Issue 9 October 1998 363 206 204 ...
Page 34: ...xxxiv Issue 9 October 1998 363 206 204 ...
Page 58: ...1 ii Issue 9 October 1998 363 206 204 ...
Page 74: ...2 iv Issue 9 October 1998 363 206 204 ...
Page 144: ...2 70 Issue 9 October 1998 363 206 204 Equipment and Rear Access Cable Installation ...
Page 192: ...3 46 Issue 9 October 1998 363 206 204 Equipment and Front Access Cable Installation ...
Page 304: ...6 30 Issue 9 October 1998 363 206 204 Release 7 Installation Tests ...
Page 330: ...7 24 Issue 9 October 1998 363 206 204 Release 8 Installation Tests ...
Page 398: ...9 32 Issue 9 October 1998 363 206 204 Release 13 TARP Installation Tests ...
Page 426: ...11 ii Issue 9 October 1998 363 206 204 ...
Page 492: ...IN 14 Issue 9 October 1998 ...