Entry checklist
....................................................................................................................................................................................................................................
The following provides a checklist to be completed prior to perform
the span/ring testing. Verify that each procedure has been completed.
Check off and initial the item.
Procedure
Completed
Initials
Notes
Have all procedures been completed which are
required in Chapter 7,
stand alone installation test exit checklist”
(7-18)
Is a laptop or desktop PC available meeting the
minimum requirements (see section
)?
Is a crossed LAN cable CAT5 with 4-wire
RJ-45/RJ-45 connectors available?
Is the following test equipment available?
•
Optical power meter with LC connectors
•
Multimeter
Span/Ring testing entry checklist