Entry checklist
....................................................................................................................................................................................................................................
The following provides a checklist to be completed prior to perform
the physical and power installation. Verify that each procedure has
been completed. Check off and initial the item.
Procedure
Completed
Initials
Notes
Is the selected installation site accessible for
delivery of racks?
If on a different level than receiving dock, is
the elevator large enough?
Does the available floor space fulfil the
requirements given in Chapter 2, section
“Floorplan guidelines (ETSI-2 / NEBS-2000)”
(2-2)
)?
Does the floor support a weight of greater than
210 kg [463 lbs]?
Are the climatic conditions fulfilled as
described in Chapter 1, section
for the operation of LambdaUnite
)?
Is there enough space in cable rack or under
floor to coil/loop excess length of transmission
cables?
Is there enough space in cable rack or under
floor for power and other external cables?
Are there any obstacles that will affect the
physical installation or cabling?
Are the required fuse/breaker positions
available?
Are the needed LambdaUnite MSS racks
available (ETSI-2 or NEBS-2000)?
Are the needed LambdaUnite MSS subracks
available?
Are all needed LambdaUnite MSS circuit
packs and cables available?
Is an ESD wrist strap available?
Is an external timing source available?
Physical and power installation entry
checklist
Mechanical installation
....................................................................................................................................................................................................................................
3 - 4
Lucent Technologies
365-374-074