Operational Tests
Manual Switching Tests
7 - 1 2
365-372-334 R2.0
Issue 4, November 2004
............................................................................................................................................................................................................................................................
Manual Switching Tests
Description
This test will initiate switching commands from the CIT TL1
Command Builder and verify proper switching and LED indications.
Use the OC3 commands for the VLNC5 or VLNC6 OLIU circuit packs
and the OC12 commands for the VLNC25 or VLNC26 circuit packs.
Main OLIU Switch Test
Important!
By default VT1.5 cross-connects will exist on the
DS1 ports and STS1 cross-connects will exist on the DS3 ports.
Step 1
Use the scroll bar in the
Command Builder
window to scroll down to
the
rtrv-oc3
or rtrv-oc12 command.
...........................................................................................................................................................................
Step 2
Click on the
rtrv-oc3
or rtrv-oc12 command.
...........................................................................................................................................................................
Step 3
Click
Send
to issue the command.
Result:
The Response Window will display the command followed
by a
COMPLD
indication as well as indicating whether main-1-1 or
main-2-1 is the active ring.
...........................................................................................................................................................................
Step 4
Use the scroll bar in the
Command Builder
window to scroll down to
the
opr-protnsw-oc3
or
opr-protnsw-oc12 c
ommand.
...........................................................................................................................................................................
Step 5
Click on the
opr-protnsw-oc3
or
opr-protnsw-oc12
command.
...........................................................................................................................................................................
Step 6
If the active ring is Ring 2, change the
m{1}-1-{1}-{1}
-{1}
parameter
listed under the
<VT1PROTN>
for DS1 or
<STS1PROTN>
for DS3,
column to
m{2}-1-{1}-{1}
-{1}
by double clicking on
1
between the
brackets
{ }
and selecting
2
from the drop down window.
...........................................................................................................................................................................
Step 7
Double click on
{LOCKOUT}
under
<PROTNSWCOCN>
and select
MAN.
Summary of Contents for Metropolis DMXplore
Page 8: ... C O N T E N T S v i i i 365 372 334 R2 0 Issue 4 November 2004 ...
Page 16: ... T A B L E S x v i 365 372 334 R2 0 Issue 4 Novmeber 2004 Glossary ...
Page 286: ... Backplane Pin Replacement Replacement Methods D 1 0 365 372 334 R2 0 Issue 4 November 2004 ...
Page 292: ... Installation Checklist Overview E 6 365 372 334 R2 0 Issue 4 November 2004 ...
Page 326: ... G L O S S A R Y G L 3 0 365 372 334 R2 0 Issue 4 November 2004 ...