Operational Tests
Manual Switching Tests
...........................................................................................................................................................................................................................................................
7 - 1 3
365-372-334 R2.0
Issue 4, November 2004
...........................................................................................................................................................................
Step 8
Click
Send
to issue the command.
Result:
The Response Window will display the command followed
by a
COMPLD
indication.
...........................................................................................................................................................................
Step 9
Use the scroll bar in the
Command Builder
window to scroll down to
the
rtrv-oc3
or
rtrv-oc12
command.
...........................................................................................................................................................................
Step 10
Click on the
rtrv-oc3
or
rtrv-oc12
command.
...........................................................................................................................................................................
Step 11
Click
Send
to issue the command.
Requirement:
The Response Window will display the command
followed by a
COMPLD
indication as well as indicating that the OLIU
that was active in Step 3 is no longer active and the other OLIU is now
active.
...........................................................................................................................................................................
Step 12
Use the scroll bar in the
Command Builder
window to scroll down to
and send the
rls-protnsw-oc3
or
rls-protnsw-oc12
command.
...........................................................................................................................................................................
Step 13
Repeat Step 4 through Step 11 to verify a switch back to the original
OLIU.
...........................................................................................................................................................................
Step 14
Check off the appropriate box in Appendix E, Installation Checklist.
End of Steps
...........................................................................................................................................................................
Summary of Contents for Metropolis DMXplore
Page 8: ... C O N T E N T S v i i i 365 372 334 R2 0 Issue 4 November 2004 ...
Page 16: ... T A B L E S x v i 365 372 334 R2 0 Issue 4 Novmeber 2004 Glossary ...
Page 286: ... Backplane Pin Replacement Replacement Methods D 1 0 365 372 334 R2 0 Issue 4 November 2004 ...
Page 292: ... Installation Checklist Overview E 6 365 372 334 R2 0 Issue 4 November 2004 ...
Page 326: ... G L O S S A R Y G L 3 0 365 372 334 R2 0 Issue 4 November 2004 ...