...........................................................................................................................................................................................................................................................
Ring Setup and Testing: Integration Procedures
Automatic Protection Switching Test
8 - 1 4
365-372-334 R2.0
Issue 4, November 2004
Result:
The Response Window should display the command
followed by a
COMPLD
indication as well as indicating whether
Ring 1 or Ring 2 is the active ring for each cross-connection.
Important!
MAIN 1 OLIU is associated with Ring 1 and MAIN 2
OLIU is associated with Ring 2.
...........................................................................................................................................................................
Step 6
Disconnect the optical fiber connected to the
IN
port of the OLIU that
is the active receiver.
Result:
The
NE
and then
MN/ABN
alarm LED will light on the
SYSCTL and the
FAULT
LED will flash on the OLIU.
...........................................................................................................................................................................
Step 7
Click
Send
to issue a second
rtrv-state-path
command.
Result:
The Response Window will display the command followed
by a
COMPLD
indication as well as indicating that the ring that was
active in the previous step is now in signal-failure and the other ring
is now active.
...........................................................................................................................................................................
Step 8
Reconnect the optical fiber to the OLIU.
Result:
After a short time, the
MN/ABN
alarm LED on the
SYSCTL and the
FAULT
LED on the OLIU will extinguish.
...........................................................................................................................................................................
Step 9
Repeat Step 4 page 13 through Step 8 page 14 to verify a switch back to
the OLIU that was originally active.
...........................................................................................................................................................................
Step 10
Leave the cross-connects in the system to complete the next section
Manual Switching Tests (page 8-15).
...........................................................................................................................................................................
Step 11
Check off the appropriate box in Appendix E, Installation Checklist.
End of Steps
...........................................................................................................................................................................
Summary of Contents for Metropolis DMXplore
Page 8: ... C O N T E N T S v i i i 365 372 334 R2 0 Issue 4 November 2004 ...
Page 16: ... T A B L E S x v i 365 372 334 R2 0 Issue 4 Novmeber 2004 Glossary ...
Page 286: ... Backplane Pin Replacement Replacement Methods D 1 0 365 372 334 R2 0 Issue 4 November 2004 ...
Page 292: ... Installation Checklist Overview E 6 365 372 334 R2 0 Issue 4 November 2004 ...
Page 326: ... G L O S S A R Y G L 3 0 365 372 334 R2 0 Issue 4 November 2004 ...