Ring Setup and Testing: Integration Procedures
Manual Switching Tests
8 - 1 6
365-372-334 R2.0
Issue 4, November 2004
...........................................................................................................................................................................
Step 6
Click on the
opr-protnsw-rr
command. Select
m{1}-1-1
.
...........................................................................................................................................................................
Step 7
If the active ring is Ring 2, change the
m{1}
parameter listed under the
<rrAIDPROTN>
column to
m{2}
by double clicking on
1
between the
brackets
{ }
and selecting
2
from the drop down window. Double click
on the
{ LOCKOUT}
under
<PROTNSWSC>
and select
MAN.
Important!
Where "rr" refers to the rate of the cross-connect (e.g.
VT1.5, or STS1)
...........................................................................................................................................................................
Step 8
Click
Send
to issue the command.
Result:
The Response Window should display the command
followed by a
COMPLD
indication.
...........................................................................................................................................................................
Step 9
Use the scroll bar in the
Command Builder
window to scroll down to
the
rls-protnsw-rr
command.
...........................................................................................................................................................................
Step 10
Click on the
rls-protnsw-rr
command. Under
<rrAIDPROTN>
select
the AID pertaining to the ring that has the manual switch request.
...........................................................................................................................................................................
Step 11
Click
Send
to issue the command.
...........................................................................................................................................................................
Step 12
Use the
rtrv-state-path
command to verify desired switch state.
Important!
The active path should now be different from what it
was prior to the manual switch being issued.
...........................................................................................................................................................................
Step 13
Use the scroll bar in the
Command Builder
window to scroll down to
the
opr-protnsw-rr
command.
Where "rr" refers to the rate of the cross connect (e.g. VT1.5, or STS1)
Summary of Contents for Metropolis DMXplore
Page 8: ... C O N T E N T S v i i i 365 372 334 R2 0 Issue 4 November 2004 ...
Page 16: ... T A B L E S x v i 365 372 334 R2 0 Issue 4 Novmeber 2004 Glossary ...
Page 286: ... Backplane Pin Replacement Replacement Methods D 1 0 365 372 334 R2 0 Issue 4 November 2004 ...
Page 292: ... Installation Checklist Overview E 6 365 372 334 R2 0 Issue 4 November 2004 ...
Page 326: ... G L O S S A R Y G L 3 0 365 372 334 R2 0 Issue 4 November 2004 ...