Installation Tests
Local Equipment and Cross-connect Tests
4 - 1 2
Lucent Technologies - Proprietary
See notice on first page
365-372-327 R2.0
Issue 1, October 2003
Double click on {
a
} and choose the Function Group where the LNW6/
LNW7/LNW8/LNW39 is located.
Result:
A command similar to the following example should be
displayed in the command window to the left of the
Send
button
Example for Function Unit
A
:
dlt-crs-vt1:lt-dmxtend:m-1-1-1-1,a-1-1-1:ctag;
This command deletes the cross-connect entered in Step 8.
............................................................................................................................................................................
Step 13
Click
Send
to issue the command.
Result:
The Response Window should display the command
followed by a
COMPLD
indication.
Requirement:
The DS-1 test set should indicate a blue (AIS) signal
is being received in place of the QRSS signal.
............................................................................................................................................................................
Step 14
Remove the test set connections from the DSX-1.
............................................................................................................................................................................
Step 15
Use the scroll bar in the
Command Builder
window to scroll down to
the
upd-sys
command.
............................................................................................................................................................................
Step 16
Click on the
upd-sys
command.
............................................................................................................................................................................
Step 17
Click
Send
to issue the command.
Result:
This command will remove alarms generated by
removing the test signals from the DSX-1.
............................................................................................................................................................................
Step 18
Repeat Step 2 through Step 17 to test each of the remaining DS-1
tributaries of the Function Unit, substituting the following address
information within the
ent-crs-vt1
and
dlt-crs-vt1
commands.
Tributary @ DSX-1
Addressing within
ent-crs-vt1
and
dlt-crs-vt1
2
m-1-1-1-2,a-1-1-2
3
m-1-1-1-3,a-1-1-3
4
m-1-1-1-4,a-1-1-4
5
m-1-1-2-1,a-1-2-1
6
m-1-1-2-2,a-1-2-2