Equipment and Cable Installation for Metropolis
®
DMXtend
Shelf Horizontal Bay Mount
Office Alarm Cable Installation
1 - 6 8
Lucent Technologies - Proprietary
See notice on first page
365-372-327 R2.0
Issue 1, October 2003
of the bottom Metropolis
®
DMXtend shelf. See Figure 1-23, Office
Alarm Cable Connections (page 1-68)
Figure 1-23 Office Alarm Cable Connections
............................................................................................................................................................................
Step 2
Route the office alarm cable from the bottom shelf out of the
Metropolis
®
DMXtend bay per Figure 1-24, Office Alarm Cable
Routing (page 1-68) to the office alarm panel.
Figure 1-24 Office Alarm Cable Routing
............................................................................................................................................................................
Step 3
Inspect the office alarm panel and add a contact protection network (if
required).
............................................................................................................................................................................
Step 4
Cut the office alarm cable to the desired length.
............................................................................................................................................................................
Step 5
Wire-wrap the loose end of the office alarm cable to the alarm panel,
making connections as listed in Table 1-25, Office Alarm Connections
(page 1-71).