Procedure
Step 1
Route the optical fiber cables from the interconnecting equipment into
the left side of the Metropolis
®
DMXtend. See Table 1-27, Optical
Important!
Protective covers must be left on cables.
Important!
Enough slack must be left in the fibers to allow them
to be moved out of the way of the A/B 1 and 2 slots to allow circuit
pack insertion and removal in those slots if required.
Figure 1-27 Optical Fiber routing
............................................................................................................................................................................
Step 2
Place the optical fiber cables in a protective tube or channel.
............................................................................................................................................................................
Step 3
Label the optical fiber cables, indicating bay, shelf, pack, and direction
(
IN
or
OUT