Equipment and Cable Installation for Metropolis
®
DMXtend
Shelf Horizontal Bay Mount
OC-12 Low Speed Optical Fiber Cable
Installation
1 - 8 2
Lucent Technologies - Proprietary
See notice on first page
365-372-327 R2.0
Issue 1, October 2003
Procedure
Step 1
Refer to the engineering job specification. Determine the function slot
where the pack will be inserted. The OC-12 pack can be inserted into
either the D or G function slots.
............................................................................................................................................................................
Step 2
Label the optical fiber cables, indicating bay, shelf, function group,
pack, and direction (
IN
or
OUT
).
............................................................................................................................................................................
Step 3
Route optical fiber cables from the interconnecting equipment into the
left side of the Metropolis
®
DMXtend and into the OC-12 optical
ports.See Table 1-27, Optical Fiber routing (page 1-77)
............................................................................................................................................................................
Step 4
Place the optical fiber cables in a protective tube or channel.
............................................................................................................................................................................
Step 5
Check off the appropriate box in Appendix E, Installation Checklist.
...........................................................................................................................................................................
End of Steps